1. M/s Lum Mawshun Minerals Ltd. (renamed as m/s Lafarge-Umiam Mining Pvt. Ltd.)
2. M/s Anderson Minerals Pvt. Ltd.
3. Leshka Hydel Power Project of the Meghalaya State Electricity Board
4. Heavy Fuel Oil Based Thermal Power Project of the Meghalaya State Electricity Board
5. New Uumtrew Hydro-Electric Project of the Meghalaya State Electricity Board
6. M/s Mawmluh Cherra Cements Ltd. (Expansion of Cement plant and Limestone Mining)
7. M/s Lafarge Umiam Mining Pvt. Ltd.

 

  1. M/S LUM MAWSHUN MINERALS LTD. (renamed as M/S LAFARGE-UMIAM MINING PVT. LTD.)
PROJECT TYPE Limestone mining
PROJECT COST Rs. 9 crores
CAPACITY 3000 tonnes per day
LOCATION Phlangkaruh, Shella Confederacy, East Khasi Hills District
AREA OF SITE 100 hectares
DATE OF HEARING 3rd June 1998
LOCATION OF HEARING Office of the Wadadar, Shella Confederacy, Shella Bazar
STATUS Cleared by the Ministry of Environment & Forests
  1. M/S ANDERSON MINERALS PVT. LTD.

PROJECT TYPE Limestone mining
PROJECT COST Rs. 1,45,78,000.00
CAPACITY 2,50,000 tonnes per year
LOCATION Lalghat, Cherragaon, West Khasi Hills District
AREA OF SITE 60 hectares
DATE OF HEARING 15th December 1998
LOCATION OF HEARING School Building, Hat Mawpyllun (Ranikor), West Khasi Hills District
STATUS Did not apply for Environmental Clearance from the Ministry of Environment & Forests
  1. LESHKA HYDEL POWER PROJECT of the MEGHALAYA STATE ELECTRICITY BOARD

PROJECT TYPE Hydro power
PROJECT COST Rs. 350 crores
CAPACITY 2 x 42 MegaWatts
LOCATION Myntdu River, Jaintia Hills District
AREA OF SITE 189.34 hectares for Leshka Stage-I Power Station
DATE OF HEARING 24th & 25th March 1999
LOCATION OF HEARING Office of the S.D.O. (Civil), Amlarem and Office of the S.D.O. (Civil), Khliehriat respectively
STATUS Cleared by the Ministry of Environment & Forests
  1. HEAVY FUEL OIL BASED THERMAL POWER PROJECT of the MEGHALAYA STATE ELECTRICITY BOARD

PROJECT TYPE Thermal power
PROJECT COST Rs. 91 crores
CAPACITY 4 x 6 MegaWatts
LOCATION Area 9, Export Promotion Industrial Park, Byrnihat, Ri-Bhoi District
AREA OF SITE 3 acres for Power House
DATE OF HEARING 14th June 2002
LOCATION OF HEARING MeSEB Guest House, Byrnihat
STATUS Did not apply for Environmental Clearance from the Ministry of Environment & Forests
  1. NEW UMTREW HYDRO-ELECTRIC PROJECT of the MEGHALAYA STATE ELECTRICITY BOARD

PROJECT TYPE Hydro power
PROJECT COST Rs. 194.30 crores
CAPACITY 2 x 20 MegaWatts
LOCATION Dehal, Byrnihat, Ri-Bhoi District
AREA OF SITE 1020 SqKms
DATE OF HEARING 24th November 2005
LOCATION OF HEARING MeSEB Guest House, Dehal (Project site)
STATUS Cleared by the Ministry of Environment & Forests
  1. M/S MAWMLUH CHERRA CEMENTS LTD. (EXPANSION OF CEMENT PLANT & LIMESTONE MINING)

PROJECT TYPE Cement plant & Limestone mining
PROJECT COST Rs. 62 crores
CAPACITY Kiln-IV with 600 tonnes per day
LOCATION Mawmluh, East Khasi Hills District
AREA OF SITE 139.67 hectares
DATE OF HEARING 16th January 2006
LOCATION OF HEARING M.C.C.L. Guest House, Mawmluh
STATUS Environmental Clearance is under process at the Ministry of Environment & Forests
  1. M/S LAFARGE UMIAM MINING PVT. LTD.

PROJECT TYPE Shale & Siltstone mining
PROJECT COST Rs. 6 crores
CAPACITY 4,10,000 tonnes per year
LOCATION Shella, East Khasi Hills District
AREA OF SITE 67.92 hectares
DATE OF HEARING 18th January 2006
LOCATION OF HEARING Project site at Shella, East Khasi Hills District
STATUS Cleared by the Ministry of Environment & Forests

 

Site hosted by National Informatics Centre, Meghalaya State Centre

Content maintained and updated by Meghalaya State Pollution Control Board

Disclaimer.

e-mail: mspcb@sancharnet.in

Site best viewed in Internet Explorer on 1024 x 768 resolution